Update – capacity for debt_ funding issues and the capacity market – lexology

Ahead of the upcoming capacity auctions, this update from the Energy and Finance team at Burges Salmon provides a reminder of the opportunities presented by the market and considers some of the potential issues that prospective investors might encounter.

The Capacity Market, which was introduced as part of the government’s Electricity Market Reform, was established to ensure security of electricity supply in light of the increasing diversity of generation technologies in the UK market.

The Capacity Market includes a number of features that make debt investment opportunities attractive. Gas line jobs in wv Long-term contracts (in some cases), monthly payment flows, fixed prices indexed annually to CPI and a “creditworthy counterparty” means that funders looking for opportunities should be looking at this market.

While often referred to as a “Capacity Contract”, this term is slightly ambiguous as there is no bilateral contract between the capacity generator and the settlement body responsible for making and receiving payments (the Electricity Settlements Company Limited). Electricity worksheets Instead a “Capacity Contract” is the combination of three different elements:

• A capacity notice that the generator receives when it is successful in an auction. A gas has no volume The capacity notice will set out the price the generator will be paid, the generating capacity and the term (one, three or 15 years).

This arrangement means that instead of delivering energy pursuant to a traditional contract, a generator’s obligation to deliver energy is effectively a statutory obligation which applies to the registered holder of a capacity agreement notice, against a statutory right to receive monthly capacity payments.

The primary obligation of the generator is to deliver electricity of a specified quantity during system stress periods as notified by National Grid Electricity Transmission (NGET). Electricity off peak hours NGET will provide four hours’ notice after which the generator must either comply with their obligations to generate or face penalties for its failure to do so.

• any penalty fees deducted from the generator for failure to meet their obligations to generate during a stress period (deductions are applied on a monthly basis).

In order to ensure the security of supply, on each occasion which there is a failure to generate, the penalty rate is set at 1/24 th of the relevant auction clearing price, adjusted for inflation. Gas variables pogil extension questions However, there is a penalty cap of 200% of a plant’s monthly income and 100% of its annual income. R gas constant chemistry Penalties will only apply where NGET gave the requisite four hours’ advance notice of a stress period.

There remains scope for generators to extract upside from supplying electricity outside of their Capacity Contract, both via a PPA outside of the Capacity Market and by over-supplying during stress periods.

In any given stress period, any capacity generated over the amount specified by NGET may entitle the generator to an over-generation payment. Gas in babies treatment These payments are funded out of the penalty fees received by the settlement body. Electricity 101 powerpoint The settlement body calculates the rate of payment as the lower of, (a) the penalty rate (as set out above) and, (b) the total penalty revenue, divided by the total volume of over-generation over the last year.

Potential investors might wish to note the potential for equity upside and/or mitigation of revenue risks that this overpayment mechanic creates.

Termination under a Capacity Contract is defined in the Capacity Market Rules 2014 and covers a number of scenarios such as insolvency of the generator, failure to meet key milestones in new build contracts, failure to deliver copies of key agreements to the delivery body and production of electricity by a generator who has submitted an ‘Opt-Out Notice’.

Generators are subject to tests throughout the term of their contract which have consequences for the generator if they are not passed. Electricity cost las vegas In particular, generators are subject to metering tests which, if not complied with, can result in the termination of their Capacity Contract. Gas zauberberg However there is no termination right per se for a failure to respond to a call for generation, even on a repeated basis.

The rules also set out certain cure periods in respect of a termination event. Electricity in water pipes Following service of a termination notice, a generator has 20 working days to write to the Secretary of State to apply for an extension of the notice, which can be for up to 60 days in certain circumstances. Electricity distribution network Within the notice period the generator is then able to set out a cure plan in which they will aim to demonstrate how and when they will comply with the requirements under which the notice has been brought.

The Secretary of State is obliged to consider the cure plans submitted pursuant to a termination notice and has wide ranging powers under the legislation to rescind a termination notice or extend the time period in which a generator must comply with their obligations under the Capacity Contract by up to six months.

Due to the fact that there is no bilateral, contractual agreement in place, funders will not be able to protect their position by way of a direct agreement, in contrast to the position under, for example, CfDs. On q gas station okc This means funders will need to apply careful scrutiny to the range of termination rights that could apply under the Capacity Market and be satisfied that generators have adequately mitigated the risks. Electricity units to kwh Funders may also ask for some contractual rights to be involved in any appeals process undertaken by the generator further to receipt of a termination notice.

There is specific provision under the Capacity Market Rules for generators assigning their rights under the Capacity Market by way of security. Gas knife lamb The precise nature of that security interest will need to be the subject of legal advice, since the right to receive payment is a statutory right and not a contractual right.

The Capacity Market Rules imply some further conditions of which funders must be aware. List of electricity usage by appliances Funders can take security over both the generating equipment and the Capacity Contract. Electricity billy elliot lyrics However both of those security interests must be registered on the Capacity Market Register, by notifying NGET in the prescribed form.

Additionally, on the enforcement of any security, both the generating equipment and the Capacity Contract must both be transferred together to an “Acceptable Provider” who meets the requirements set out in the rules. Electricity word search puzzle This prevents the transfer to any generator who has been in default within the last year, who cannot meet the prescribed credit cover or who does not hold a pre-qualification certificate.

The government is currently consulting on changes which would require the settlement body to withhold Capacity Market payments from certain new build generators that are awarded long term Capacity Contracts.

The generators potentially affected by the change are those that have used (or will use) Enterprise Investment Scheme (EIS) or Venture Capital Trust (VCT) funding in the construction of their Capacity Market Unit. Gasbuddy trip If awarded long term contracts, affected generators would not receive capacity market payments until an amount equal to the total amount of that EIS or VCT money spent on the construction of their new Capacity Market Unit had been recovered.

It is currently proposed that this change, if implemented, will apply to generators awarded long term Capacity Contracts in the upcoming (December 2016) T-4 and early auctions.

While it is not an issue that is specific to the Capacity Market, investors should also be aware of the proposed changes to embedded benefits (the financial benefits accruing to small-scale distribution connected generation as a result of the way in which they are connected to the network). O goshi technique In particular, several ongoing modification proposals to the Connection and Use of System Code (CUSC) seek to end the payment of the TNUoS Demand Residual (commonly known as Triad avoidance benefit). Mp electricity bill payment Triad avoidance benefit is principally a benefit enjoyed by non-intermittent embedded generation that can guarantee export during periods of peak demand (triad periods) such as the small scale gas and diesel generators that make up a large proportion of the generation in the Capacity Market. Gas bike alley Ofgem is scheduled to make its determination on the key modification proposals on 28 December.